Accroding to the Recreation and Wellness Center website some of the construction that was done for the month of April was:
Landscaping for the plaza began this month with the installation of Date Palm Trees in the pool deck area.
Tiling continues in the locker rooms and bathrooms.
Installation of lights and fans continue on the 2nd floor.
Framing finished for the cardio theatre wall.
Racquetball flooring to be delivered this month and installed accordingly.
Glass doors arriving mid April to be installed.